Cited by

Opinions in Arizona that cite McAlister v. Citibank, 829 P.2d 1253.

59 citing documents.

  • Dyrek v. Dyrek Ariz. Ct. App. Div. 1 2026
  • Dyrek v. Dyrek Ariz. Ct. App. Div. 1 2026
    “Negligent misrepresentation requires a misrepresentation or omission of a fact.” McAlister v. Citibank (Arizona), see also KB Home Tucson, Inc. v. Charter Oak Fire Ins.
  • 15 UP-VW v. LUNA Ariz. Ct. App. Div. 1 2026
  • 15 UP-VW v. LUNA Ariz. Ct. App. Div. 1 2026
    The superior court has similarly broad discretion when deciding who is a successful party by considering “the totality of circumstances and the relative success of the litigants.”
  • Accord Trucking, Inc. v. Fedex Ariz. Ct. App. Div. 1 2024
  • Accord Trucking, Inc. v. Fedex Ariz. Ct. App. Div. 1 2024
    McAlister v. Citibank (Arizona)
  • Fleming v. Fripps Ariz. Ct. App. Div. 1 2023
  • Fleming v. Fripps Ariz. Ct. App. Div. 1 2023
    (holding that a case arose out of contract under § 12-341.01 where a party alleged fraud claims resulting from a breach of contract to loan money).
  • Custom Accounting v. Sal E. Mander Ariz. Ct. App. Div. 1 2023
  • Custom Accounting v. Sal E. Mander Ariz. Ct. App. Div. 1 2023
  • Szeto v. Aps Ariz. Ct. App. Div. 1 2021
  • Szeto v. Aps Ariz. Ct. App. Div. 1 2021
    Commercial losses suffered by a plaintiff when the defendant fails to provide a contracted service are generally recoverable in a breach of contract action as consequential damages, but are unrecoverable in a negligence action because of the economic 9 SZETO, et al. v. APS Opinion of the Court loss doctrine.
  • Heritage v. Weinberg Ariz. Ct. App. Div. 1 2021
  • Heritage v. Weinberg Ariz. Ct. App. Div. 1 2021
    2 The superior court awarded fees to both parties under the CC&Rs but noted that the fees it awarded would be the same whether granted under the CC&Rs or § 12-341.01.
  • Seidman v. Weiler Ariz. Ct. App. Div. 1 2019
  • Seidman v. Weiler Ariz. Ct. App. Div. 1 2019
    (“Negligent misrepresentation requires a misrepresentation or omission of a fact.”).
  • Shepherd v. Costco 441 P.3d 989 Ariz. Ct. App. Div. 1 2019
  • Shepherd v. Costco 441 P.3d 989 Ariz. Ct. App. Div. 1 2019
    McAlister v. Citibank (Arizona)
  • Southwest v. Sbbi, Inc. Ariz. Ct. App. Div. 1 2018
  • Southwest v. Sbbi, Inc. Ariz. Ct. App. Div. 1 2018
    McAlister v. Citibank (Ariz.), a Subsidiary of Citicorp
  • Great Western Bank v. LJC Development, LLC 362 P.3d 1037 Ariz. Ct. App. Div. 1 2015
  • Great Western Bank v. LJC Development, LLC 362 P.3d 1037 Ariz. Ct. App. Div. 1 2015
    Our courts have generally declined to recognize any special relationship between a debtor and creditor, (holding bank owed no fiduciary duty to borrower); cf. Stewart v. Phx.
  • Kool v. Evans Ariz. Ct. App. Div. 1 2015
  • Kool v. Evans Ariz. Ct. App. Div. 1 2015
    McAlister v. Citibank (Arizona)
  • Hendershott v. Babeu Ariz. Ct. App. Div. 1 2015
  • Hendershott v. Babeu Ariz. Ct. App. Div. 1 2015
    ¶22 To state a claim for constructive fraud, a plaintiff must allege “a breach of legal or equitable duty which, irrespective of the moral guilt or intent of the party charged,” would be considered “fraudulent because of its tendency to deceive others, to violate public or private confidence, or to injure public interests.” McAlister v. Citibank, a Subsidiary of Citicorp
  • Glava v. Jpmorgan Ariz. Ct. App. Div. 1 2015
  • Glava v. Jpmorgan Ariz. Ct. App. Div. 1 2015
    See McAlister v. Citibank (Ariz.), (determining bank owed no fiduciary duty to customer); cf. Stewart v. Phx.
  • Wilson v. Pnc Ariz. Ct. App. Div. 1 2015
  • Wilson v. Pnc Ariz. Ct. App. Div. 1 2015
    It is well settled “that the relationship between a Bank and an ordinary depositor, absent any special agreement, is that of debtor and creditor.” McAlister v. Citibank (Ariz.), a Subsidiary of Citicorp, (internal quotation marks omitted).
  • Abromovitz v. Red Eyed Ariz. Ct. App. Div. 1 2014
  • Abromovitz v. Red Eyed Ariz. Ct. App. Div. 1 2014
    2012) (citation omitted), or consequential damages (Arizona), McAlister v. Citibank (Ariz.), a Subsidiary of Citicorp, (citations omitted), available for breach of contract.
  • State v. Bayardi 281 P.3d 1063 Ariz. Ct. App. Div. 1 2012
  • State v. Bayardi 281 P.3d 1063 Ariz. Ct. App. Div. 1 2012
    § 12-2101 (A)(4); see also In re Approximately $50,000.00 In U.S. Currency, ¶ 5 , (construing predecessor statute; noting "final order is one that disposes of the case, leaving no question open for the court’s determination”) (citing McAlister v. Citibank (Arizona), , ).
  • Sensing v. Harris 172 P.3d 856 Ariz. Ct. App. Div. 1 2007
  • Sensing v. Harris 172 P.3d 856 Ariz. Ct. App. Div. 1 2007
    McAlister v. Citibank (Arizona)
  • Burkhamer v. State of Arizona Ariz. Ct. App. Div. 2 2007
  • Burkhamer v. State of Arizona Ariz. Ct. App. Div. 2 2007
    (“Rule 54(b) language does not make the judgment final and appealable” when judgment disposed of some but not all of plaintiff’s legal theories); (trial court improperly included Rule 54(b) language in “order relating to consequential damages” that “merely 19 eliminated a potential remedy while not disposing of a single claim”)
  • Mezey v. Fioramonti 65 P.3d 980 Ariz. Ct. App. Div. 1 2003
  • Mezey v. Fioramonti 65 P.3d 980 Ariz. Ct. App. Div. 1 2003
  • Wells Fargo Bank v. Arizona Laborers, Teamsters & Cement Masons Local No. 395 Pension Trust Fund 38 P.3d 12 Ariz. 2002
  • Wells Fargo Bank v. Arizona Laborers, Teamsters & Cement Masons Local No. 395 Pension Trust Fund 38 P.3d 12 Ariz. 2002
    at 355 , 813 P.2d at 720 ; see also Wagenseller at 383 , 710 P.2d at 1038 ; McAlister v. Citibank (Arizona), a Subsidiary of Citicorp, , (a special relationship must exist in order to support a tortious.
  • Wells Fargo Bank v. Az Laborers Ariz. 2002
  • Wells Fargo Bank v. Az Laborers Ariz. 2002
    at 355, 813 P.2d at 720; see also Wagenseller at 383, 710 P.2d at 1038; McAlister v. Citibank (Arizona), a Subsidiary of Citicorp, P.2d 1253 (App. 1992) (a special relationship must exist in order to support a tortious breach of the implied covenant of good faith and fair dealing).
  • McEvoy v. Aerotek, Inc. 34 P.3d 979 Ariz. Ct. App. Div. 1 2001
  • McEvoy v. Aerotek, Inc. 34 P.3d 979 Ariz. Ct. App. Div. 1 2001
    It is true that in some cases, “[w]hen determining the successful party for the purposes of awarding costs, we view the totality of circumstances and the relative success of the litigants.” McAlister v. Citibank (Arizona), , see also Notaros v. Fine Arts Gallery of Scottsdale, Inc., , (holding that, based on totality of litigation, trial court did not abuse its discretion in determining that defendants were the successful party).
  • Haisch v. Allstate Insurance 5 P.3d 940 Ariz. Ct. App. Div. 1 2000
  • Haisch v. Allstate Insurance 5 P.3d 940 Ariz. Ct. App. Div. 1 2000
    Co., , McAlister v. Citibank (Arizona), a Subsidiary of Citicorp
  • In re Approximately $50,000.00 in United States Currency 2 P.3d 1271 Ariz. Ct. App. Div. 2 2000
  • In re Approximately $50,000.00 in United States Currency 2 P.3d 1271 Ariz. Ct. App. Div. 2 2000
    Hence, its order was the “final order in the case.” (if, following court’s order, there is “nothing left of the case to dispose of,” order is final and appealable); McAlister v. Citibank (Arizona), , (final order is one that disposes of the case, leaving no question open for the court’s determination).